Cable Penetration and Trays
- 70% of the High Voltage cable penetrations and Trays are completed. Due to limited space, caused by the ceiling heights in the guest areas, additional cable trays have been purchased and new & wider cable trays are being installed to accommodate the ceiling heights. However, no action has been taken for Low Voltage cable penetrations and trays.
Cable Pulling
- Cable pulling has been started at the crew area and on tank deck.
Switchboards (AC/DC/EMG)
- Main AC/DC & Emergency Switchboards have been produced. Main switchboards are installed in ECR. For the distribution Switchboards, only the cabinet of the crew area distribution board has been purchased and installed in its place. No any action has been taken for the others.
Transformers Service & Emergency
- Transformers, Galley & Laundry Transformer and Shore Power Transformer have been purchased. Only Shore power transformer has been installed on board.
Start Panels (Pumps, Fans, Nav Lights, etc)
- No action has been taken.
Batteries
- The batteries for gensets which came with the units have all expired and need to be replaced. No action has been taken for the others.
Battery Insulator
Battery Chargers
- Chargers for the gensets’ batteries came with the units. No action has been taken for the others.
Battery Master Switch
- No action has been taken.
Inverter
- No action has been taken.
Converter
- No action has been taken.
Electronic Cables
- No action has been taken.
Shore Cable, Sockets
- No action has been taken.
Switches & Plugs
- No action has been taken.
Dashboards
- No action has been taken.
Interior Lights
Exterior Lights
- Ordered from Neo Light. Pay & acquire the goods.
Decorative Lights
- No action has been taken.
Emergency Lights
- No action has been taken.
Underwater Lights
- 28 pieces three colored LED underwater lights along with their DMX drivers have been purchased and are currently stored in the Shipyard; the installation of the flanges has been completed.
Navigation Lights
- No action has been taken.
Search Lights
- 2x Sanshin HRX-150 with remote control panel have been purchased and stored in the Shipyard.
Dimmer Modules
- No action has been taken.
ER, Bilge and Technical Area Lights
- No action has been taken.
Materials used inside switchboards
- No action has been taken.
General Electric materials
- No action has been taken.
Other Consumables
- No action has been taken.
Alarm Monitoring System
Power Management System (Paralleling System)
- System module has been installed in the Main
Switchboard.
- No action taken for other works.
Electric Plans
- Some plans have been drawn up by Can Makina Elektrik Company and approved by the Class. Need to make agreement for the remaining plans and calculations.
Subcontractor
- Delmar Marin Elektrik Company has started but need to make a new agreement.